MISO-S1133
100 MW generation in Sangamon · In queue since February 2026
100 MW
Capacity
0
Components
3 months
In Queue
—
IA Status
Total Duration
3 months
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-S1133 is a proposed 100 MW generation project located in Sangamon County, Illinois. The project, which utilizes an "Other" technology type, is listed in the Midcontinent Independent System Operator (MISO) interconnection queue. Duke Energy Indiana, LLC is the listed utility. The project entered the queue on February 11, 2026, and is currently in active status for a System Impact Study (SIS).
The point of interconnection (POI) for MISO-S1133 is the 343515 Chatham Main - 346555 North Aurburn (Ameren) 138.0kV line.
Generated from interconnection queue and public data sources
State
—
County
Sangamon
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
DUKE ENERGY INDIANA, LLC
Entity
MISO
Service Type
SIS
Point of Interconnection
343515 Chatham Main - 346555 North Aurburn (Ameren) 138.0kV
Data Source
Live · MISO
- ISO / RTO
- MISO
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.