MPC-MPC03800
250 MW generation in Eddy, ND · In queue since February 2019 · Proposed COD November 2023
250 MW
Capacity
1
Components
Wind
7y 3m
In Queue
Facility Study
IA Status
COD target: 2023
Total Duration
4y 9m
Schedule
30 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-11-30
MPC-MPC03800 is a proposed 250 MW wind generation project located in Eddy County, North Dakota. The project is being developed by Minnkota Power Cooperative (MPC) and is interconnected within the Midcontinent Independent System Operator (MISO) queue. The project entered the queue on February 21, 2019, with a proposed commercial operation date of November 30, 2023. Its interconnection status is currently in the Facility Study phase, and the point of interconnection is the Center-Prairie 345 kV Line.
The proposed project consists of 250 MW of wind generation capacity. It is listed as an active project in the MISO interconnection queue. The project has appeared in recent news coverage regarding renewable energy development in the region.
Generated from interconnection queue and public data sources
State
ND
County
Eddy
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
Minnkota Power Cooperative
Entity
MPC
Service Type
—
Point of Interconnection
Center-Prairie 345 kV Line
Data Source
LBNL
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.