MPC-MPC04000
300 MW generation in Oliver, ND · In queue since April 2019 · Proposed COD December 2023
300 MW
Capacity
1
Components
Wind
7y 1m
In Queue
Facility Study
IA Status
COD target: 2023
Total Duration
4y 8m
Schedule
29 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-01
MPC-MPC04000 is a proposed 300 MW wind generation project located in Oliver County, North Dakota. The project is being developed by Minnkota Power Cooperative (MPC) and is listed in the Midcontinent Independent System Operator (MISO) interconnection queue. The project entered the queue on April 25, 2019, with a proposed commercial operation date of December 1, 2023. Its interconnection status is currently in the Facility Study phase, and the point of interconnection is the Square Butte 230 kV Substation.
The proposed project consists of 300 MW of wind generation capacity. It is currently listed as an active project within the MISO queue.
Generated from interconnection queue and public data sources
State
ND
County
Oliver
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
Minnkota Power Cooperative
Entity
MPC
Service Type
—
Point of Interconnection
Square Butte 230 kV Substation
Data Source
LBNL
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MPC-MPC04000