MPC-MPC04500
258.4 MW generation in Grand Forks, ND · In queue since September 2023 · Proposed COD March 2028
258.4 MW
Capacity
1
Components
Wind
2y 8m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-03-01
MPC-MPC04500 is a proposed wind generation project with a total capacity of 258.4 MW. The project is located in Grand Forks County, North Dakota, and is being developed by Minnkota Power Cooperative (MPC). It is currently active in the Midcontinent Independent System Operator (MISO) interconnection queue, with a queue entry date of September 26, 2023, and a proposed commercial operation date of March 1, 2028. The point of interconnection is the Lerfald Substation.
The development project consists solely of wind generation, with 258.4 MW of wind turbine capacity.
Generated from interconnection queue and public data sources
State
ND
County
Grand Forks
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
Minnkota Power Cooperative
Entity
MPC
Service Type
—
Point of Interconnection
Lerfald Substation
Data Source
LBNL
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MPC-MPC04500