N-C-NC5-001
480 MW hybrid in Kane, UT · In queue since May 2015 · Proposed COD October 2028
480 MW
Capacity
1
Components
Solar
11 years
In Queue
—
IA Status
COD target: 2028
Total Duration
13y 5m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-10-31
The proposed project N-C-NC5-001 is a 480 MW hybrid Solar+Battery development project located in Kane County, Utah. It is in the Navajo-Crystal (N-C) interconnection queue, having entered the queue on May 11, 2015, with a proposed commercial operation date of October 31, 2028. The point of interconnection is the Navajo-Crystal 525 kV Line.
The project consists of 480 MW of solar capacity. It is interconnected with the Navajo-Crystal utility. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
UT
County
Kane
Grid Region
Mountain West
Market
—
Developer
—
Utility
Navajo-Crystal
Entity
N-C
Service Type
—
Point of Interconnection
Navajo-Crystal 525 kV Line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.