N-C-NC5-009
300 MW generation in Mohave, AZ · In queue since April 2022 · Proposed COD September 2027
300 MW
Capacity
1
Components
Wind
4y 1m
In Queue
—
IA Status
COD target: 2027
Total Duration
5y 5m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-09-01
Proposed project N-C-NC5-009 is a 300 MW wind generation project located in Mohave County, Arizona. The project, developed by Navajo-Crystal (N-C), entered the utility's interconnection queue on April 5, 2022, and has a proposed commercial operation date of September 1, 2027. The point of interconnection is the Navajo-Crystal 525 kV Line.
The project is currently listed as active in the interconnection queue. There is no record of an interconnection agreement (IA) at this time, nor is there a match to an existing operating plant in EIA data. Recent news coverage of the project is not available.
Generated from interconnection queue and public data sources
State
AZ
County
Mohave
Grid Region
Mountain West
Market
—
Developer
—
Utility
Navajo-Crystal
Entity
N-C
Service Type
—
Point of Interconnection
Navajo-Crystal 525 kV Line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project N-C-NC5-009