Project N-C-NC5-010 — Project Summary

Queue ID
N-C-NC5-010
Capacity
500 MW
Technology
Solar+Battery
Status
active
Location
Kane, UT
Region
West
Developer
IA Status

N-C-NC5-010

N-C-NC5-010BetaActiveSolarBatteryN-CLBNL

500 MW hybrid in Kane, UT · In queue since March 2024 · Proposed COD May 2028

500 MW

Capacity

1

Components

Solar

2y 2m

In Queue

IA Status

COD target: 2028

Interconnection

Total Duration

4y 2m

Pre-Study0%
Queue EntryMar 26, 2024

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-05-30

About

The proposed project N-C-NC5-010 is a 500 MW hybrid Solar+Battery development project located in Kane County, Utah. The project consists of 500 MW of solar capacity. It is being proposed by developer N-C and is interconnected with the Navajo-Crystal utility.

The project is currently active in the Navajo-Crystal interconnection queue, having entered the queue on March 26, 2024. The proposed commercial operation date is May 30, 2028. The point of interconnection is the Navajo-Crystal 525 kV Line.

Generated from interconnection queue and public data sources

Project Details

State

UT

County

Kane

Grid Region

Mountain West

Market

Developer

Utility

Navajo-Crystal

Entity

N-C

Service Type

Point of Interconnection

Navajo-Crystal 525 kV Line

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
FOURCORNERS
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.