100 MW generation in Clark, NV · In queue since September 2014 · Proposed COD March 2025
100 MW
Capacity
1
Components
Solar
11y 8m
In Queue
IA Executed
IA Status
COD target: 2025
Total Duration
10y 6m
Schedule
14 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2025-03-01
The proposed project NVE-Company 140 is a 100 MW solar generation project located in Clark County, Nevada. The project is in the NV Energy (NVE) interconnection queue with a queue entry date of September 30, 2014. The proposed commercial operation date is March 1, 2025, and the interconnection agreement has been executed.
The project consists of 100 MW of solar photovoltaic generation. It is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
NV
County
Clark
Grid Region
Mountain West
Market
—
Developer
—
Utility
NV Energy
Entity
NVE
Service Type
—
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project NVE-Company 140