150 MW hybrid in Clark, NV · In queue since September 2018 · Proposed COD March 2026
150 MW
Capacity
1
Components
Solar
7y 8m
In Queue
IA Executed
IA Status
COD target: 2026
Total Duration
7y 6m
Schedule
2 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2026-03-01
NVE-Company 168 is a proposed 150 MW hybrid solar and battery project located in Clark County, Nevada. The development project consists of 150 MW of solar generation capacity. It is listed in the NV Energy (NVE) interconnection queue with a queue entry date of September 26, 2018, and a proposed commercial operation date of March 1, 2026. The project's interconnection agreement (IA) has been executed.
The proposed project is listed as active in the interconnection queue. Recent news coverage has discussed the project's progress.
Generated from interconnection queue and public data sources
State
NV
County
Clark
Grid Region
Mountain West
Market
—
Developer
—
Utility
NV Energy
Entity
NVE
Service Type
—
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project NVE-Company 168