NVE-Company 170
250 MW generation in Clark, NV · In queue since September 2018 · Proposed COD June 2023
250 MW
Capacity
1
Components
Solar
7y 8m
In Queue
Suspended
IA Status
COD target: 2023
Total Duration
4y 9m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-06-01
NVE-Company 170 is a proposed solar generation project located in Clark County, Nevada, with a total capacity of 250 MW. The project consists of 250 MW of solar photovoltaic generation. It is listed in the NV Energy (NVE) interconnection queue with a queue entry date of September 26, 2018, and a proposed commercial operation date of June 1, 2023.
The interconnection status of NVE-Company 170 is currently listed as "suspended," and its interconnection agreement (IA) status is also "suspended."
Generated from interconnection queue and public data sources
State
NV
County
Clark
Grid Region
Mountain West
Market
—
Developer
—
Utility
NV Energy
Entity
NVE
Service Type
—
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project NVE-Company 170