NVE-Company 173
350 MW hybrid in Clark, NV · In queue since November 2018 · Proposed COD September 2024
350 MW
Capacity
1
Components
Solar
7y 6m
In Queue
Suspended
IA Status
COD target: 2024
Total Duration
5y 10m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-09-01
The proposed NVE-Company 173 project is a 350 MW solar and battery hybrid development in Clark County, Nevada. The project consists of 350 MW of solar generation.
The project is in the NV Energy (NVE) interconnection queue, with an original queue entry date of November 30, 2018. The proposed commercial operation date is September 1, 2024. Its interconnection agreement status is currently listed as suspended.
Generated from interconnection queue and public data sources
State
NV
County
Clark
Grid Region
Mountain West
Market
—
Developer
—
Utility
NV Energy
Entity
NVE
Service Type
—
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project NVE-Company 173