NVE-Company 185
30 MW storage in Clark, NV · In queue since September 2019 · Proposed COD September 2023
30 MW
Capacity
1
Components
Battery
6y 8m
In Queue
IA Executed
IA Status
COD target: 2023
Total Duration
4 years
Schedule
33 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2023-09-01
NVE-Company 185 is a proposed 30 MW battery storage project located in Clark County, Nevada. The project is in the NV Energy (NVE) interconnection queue, with an entry date of September 26, 2019. The proposed commercial operation date is September 1, 2023, and the interconnection agreement has been executed.
The development project is listed as active in the interconnection queue. It is a standalone storage project consisting entirely of battery technology.
Generated from interconnection queue and public data sources
State
NV
County
Clark
Grid Region
Mountain West
Market
—
Developer
—
Utility
NV Energy
Entity
NVE
Service Type
—
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project NVE-Company 185