NVE-Company 192
200 MW hybrid in Clark, NV · In queue since September 2020 · Proposed COD June 2024
200 MW
Capacity
1
Components
Solar
5y 8m
In Queue
IA Executed
IA Status
COD target: 2024
Total Duration
3y 9m
Schedule
22 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2024-06-30
The NVE-Company 192 development project is a proposed 200 MW hybrid solar and battery energy project located in Clark County, Nevada. Interconnecting to the NV Energy grid, the project entered the NVE interconnection queue on September 22, 2020, and has a proposed commercial operation date of June 30, 2024. The project consists of 200 MW of solar generation capacity.
The interconnection agreement for the NVE-Company 192 project has been executed. The project has appeared in recent news coverage regarding energy development in Nevada.
Generated from interconnection queue and public data sources
State
NV
County
Clark
Grid Region
Mountain West
Market
—
Developer
—
Utility
NV Energy
Entity
NVE
Service Type
—
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project NVE-Company 192