NVE-Company 193
57 MW hybrid in Clark, NV · In queue since March 2021 · Proposed COD March 2026
57 MW
Capacity
1
Components
Solar
5y 2m
In Queue
IA Executed
IA Status
COD target: 2026
Total Duration
5 years
Schedule
1 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2026-03-31
NVE-Company 193 is a proposed 57 MW hybrid solar and battery energy project located in Clark County, Nevada. The project, consisting of 57 MW of solar power, is in the NV Energy (NVE) interconnection queue with a queue entry date of March 24, 2021.
The proposed commercial operation date for NVE-Company 193 is March 31, 2026, and the project's interconnection agreement has been executed. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
NV
County
Clark
Grid Region
Mountain West
Market
—
Developer
—
Utility
NV Energy
Entity
NVE
Service Type
—
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project NVE-Company 193