NVE-Company 197
200 MW storage in Clark, NV · In queue since March 2021 · Proposed COD June 2024
200 MW
Capacity
1
Components
Battery
5y 2m
In Queue
IA Executed
IA Status
COD target: 2024
Total Duration
3y 3m
Schedule
23 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2024-06-01
NVE-Company 197 is a proposed 200 MW battery storage project located in Clark County, Nevada. The project is being developed within the NV Energy (NVE) service area. It entered the NVE interconnection queue on March 31, 2021, with a proposed commercial operation date of June 1, 2024. The interconnection agreement for the project has been executed.
The development project consists entirely of battery storage, with a total capacity of 200 MW. Recent news coverage has discussed the project's progress and potential impact on the region's energy grid.
Generated from interconnection queue and public data sources
State
NV
County
Clark
Grid Region
Mountain West
Market
—
Developer
—
Utility
NV Energy
Entity
NVE
Service Type
—
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project NVE-Company 197