NVE-Company 202
200 MW storage in Clark, NV · In queue since September 2021 · Proposed COD November 2024
200 MW
Capacity
1
Components
Battery
4y 8m
In Queue
Suspended
IA Status
COD target: 2024
Total Duration
3y 2m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-11-30
NVE-Company 202 is a proposed 200 MW battery storage project located in Clark County, Nevada. The project is being developed within the NV Energy (NVE) service area. It entered the NVE interconnection queue on September 29, 2021, with a proposed commercial operation date of November 30, 2024.
The project's interconnection status is currently listed as "suspended," and its Interconnection Agreement (IA) status is also "suspended." Recent news coverage has discussed the project's progress and potential impact on the region's energy grid.
Generated from interconnection queue and public data sources
State
NV
County
Clark
Grid Region
Mountain West
Market
—
Developer
—
Utility
NV Energy
Entity
NVE
Service Type
—
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.