NVE-Company 211
220 MW storage in Clark, NV · In queue since January 2022 · Proposed COD May 2029
220 MW
Capacity
1
Components
Battery
4y 4m
In Queue
IA Executed
IA Status
COD target: 2029
Total Duration
7y 4m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2029-05-01
The NVE-Company 211 development project is a proposed 220 MW battery storage project located in Clark County, Nevada. The project, under development by NVE, is interconnected to the NV Energy system. It entered the NV Energy interconnection queue on January 25, 2022, and has a proposed commercial operation date of May 1, 2029. The project's Interconnection Agreement (IA) has been executed.
This proposed project has appeared in recent news coverage regarding NV Energy's grid modernization efforts.
Generated from interconnection queue and public data sources
State
NV
County
Clark
Grid Region
Mountain West
Market
—
Developer
—
Utility
NV Energy
Entity
NVE
Service Type
—
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project NVE-Company 211