NVE-Company 213
300 MW storage in Clark, NV · In queue since March 2022 · Proposed COD May 2029
300 MW
Capacity
1
Components
Battery
4y 2m
In Queue
Suspended
IA Status
COD target: 2029
Total Duration
7y 2m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-05-01
The proposed NVE-Company 213 project is a 300 MW battery storage development located in Clark County, Nevada. The project is sponsored by NV Energy (NVE). It entered the NV Energy interconnection queue on March 24, 2022, with a proposed commercial operation date of May 1, 2029.
Currently, the project's interconnection agreement status is listed as suspended. Recent news coverage of the project is available.
Generated from interconnection queue and public data sources
State
NV
County
Clark
Grid Region
Mountain West
Market
—
Developer
—
Utility
NV Energy
Entity
NVE
Service Type
—
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project NVE-Company 213