NVE-Company 218
460 MW hybrid in Clark, NV · In queue since March 2023 · Proposed COD May 2029
460 MW
Capacity
1
Components
Solar
3y 2m
In Queue
Suspended
IA Status
COD target: 2029
Total Duration
6y 2m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-05-01
NVE-Company 218 is a proposed 460 MW hybrid solar and battery project located in Clark County, Nevada. The development project, consisting of 460 MW of solar power, is in the NV Energy (NVE) interconnection queue, with an entry date of March 28, 2023. The proposed commercial operation date is May 1, 2029.
The interconnection agreement (IA) for NVE-Company 218 is currently listed as suspended, matching the overall project status within the queue. The project has appeared in recent news coverage regarding renewable energy development in Nevada.
Generated from interconnection queue and public data sources
State
NV
County
Clark
Grid Region
Mountain West
Market
—
Developer
—
Utility
NV Energy
Entity
NVE
Service Type
—
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.