NVE-Company 225
300 MW hybrid in Clark, NV · In queue since September 2022 · Proposed COD December 2030
300 MW
Capacity
1
Components
Solar
3y 8m
In Queue
Suspended
IA Status
COD target: 2030
Total Duration
8y 3m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-12-31
The proposed NVE-Company 225 project is a 300 MW hybrid solar and battery energy storage development in Clark County, Nevada. The project consists of 300 MW of solar photovoltaic generation. It is located in the West region and is being proposed by NV Energy (NVE).
The project is currently in the NV Energy interconnection queue with a queue entry date of September 27, 2022. The proposed commercial operation date is December 31, 2030. The interconnection agreement status is currently listed as suspended. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
NV
County
Clark
Grid Region
Mountain West
Market
—
Developer
—
Utility
NV Energy
Entity
NVE
Service Type
—
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project NVE-Company 225