NVE-Company 226
400 MW storage in Clark, NV · In queue since September 2022 · Proposed COD December 2030
400 MW
Capacity
1
Components
Battery
3y 8m
In Queue
Suspended
IA Status
COD target: 2030
Total Duration
8y 3m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-12-31
NVE-Company 226 is a proposed 400 MW battery storage project located in Clark County, Nevada. The project is being developed within the NV Energy (NVE) interconnection queue, with an entry date of September 28, 2022. The proposed commercial operation date is December 31, 2030.
The project's interconnection status is currently listed as "suspended," and its Interconnection Agreement (IA) status is also "suspended." The project has appeared in recent news coverage regarding energy storage development in the region.
Generated from interconnection queue and public data sources
State
NV
County
Clark
Grid Region
Mountain West
Market
—
Developer
—
Utility
NV Energy
Entity
NVE
Service Type
—
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project NVE-Company 226