NVE-Company 231
222 MW generation in Clark, NV · In queue since September 2022 · Proposed COD February 2024
222 MW
Capacity
1
Components
Gas
3y 8m
In Queue
IA Executed
IA Status
COD target: 2024
Total Duration
1y 5m
Schedule
27 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 24–48 months
Proposed COD: 2024-02-19
NVE-Company 231 is a proposed generation project located in Clark County, Nevada, with a total capacity of 222 MW. The project, developed by NVE, utilizes gas-fired technology. It is currently active in the NV Energy interconnection queue, with an entry date of September 29, 2022, and a proposed commercial operation date of February 19, 2024. The project's Interconnection Agreement (IA) has been executed.
The project consists of 222 MW of gas-fired generation capacity. It is listed in the West region. The project has an active status in the interconnection queue.
Generated from interconnection queue and public data sources
State
NV
County
Clark
Grid Region
Mountain West
Market
—
Developer
—
Utility
NV Energy
Entity
NVE
Service Type
—
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project NVE-Company 231