NVE-Company 238
1,000 MW hybrid in Nye, NV · In queue since January 2023 · Proposed COD September 2028
1,000 MW
Capacity
1
Components
Solar
3y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
5y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-01
NVE-Company 238 is a proposed 1000 MW hybrid solar and battery energy project located in Nye County, Nevada. The development project, under utility NV Energy and developer NVE, consists of 1000 MW of solar capacity.
The project is currently active in the NV Energy interconnection queue (NVE) with a queue entry date of January 19, 2023. Its proposed commercial operation date is September 1, 2028, and the interconnection agreement status is listed as "In Progress (unknown study)". The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
NV
County
Nye
Grid Region
Mountain West
Market
—
Developer
—
Utility
NV Energy
Entity
NVE
Service Type
—
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.