NVE-Company 251
500 MW storage in Clark, NV · In queue since March 2023 · Proposed COD October 2028
500 MW
Capacity
1
Components
Other Storage
3y 2m
In Queue
Suspended
IA Status
COD target: 2028
Total Duration
5y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-10-30
NVE-Company 251 is a proposed 500 MW battery storage project located in Clark County, Nevada. The project, under development by NVE, consists of 500 MW of other storage technology. It is currently in the NV Energy interconnection queue, with an entry date of March 28, 2023, and a proposed commercial operation date of October 30, 2028.
The project's interconnection status is currently listed as suspended, and its interconnection agreement (IA) status is also suspended. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
NV
County
Clark
Grid Region
Mountain West
Market
—
Developer
—
Utility
NV Energy
Entity
NVE
Service Type
—
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.