NVE-Company 255
600 MW hybrid in Nye, NV · In queue since September 2023 · Proposed COD September 2027
600 MW
Capacity
1
Components
Solar
2y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
4 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-09-01
NVE-Company 255 is a proposed 600 MW solar and battery hybrid project located in Nye County, Nevada. The development project consists of 600 MW of solar generation capacity.
The project is in the NV Energy interconnection queue (NVE) with a queue entry date of September 25, 2023. Its proposed commercial operation date is September 1, 2027, and the interconnection agreement status is listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
NV
County
Nye
Grid Region
Mountain West
Market
—
Developer
—
Utility
NV Energy
Entity
NVE
Service Type
—
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.