NVE-Company 258
104 MW hybrid in Clark, NV · In queue since September 2023 · Proposed COD February 2027
104 MW
Capacity
1
Components
Gas
2y 8m
In Queue
Suspended
IA Status
COD target: 2027
Total Duration
3y 5m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-02-28
NVE-Company 258 is a proposed hybrid development project located in Clark County, Nevada, within the NV Energy service area. The project, which entered the NV Energy interconnection queue on September 28, 2023, consists of a 104 MW gas-fired generator paired with a battery energy storage system. The proposed commercial operation date is February 28, 2027.
The project's interconnection status is currently listed as "suspended," and its interconnection agreement (IA) status is also "suspended." The developer is identified as NVE. The total capacity of the project is 104 MW.
Generated from interconnection queue and public data sources
State
NV
County
Clark
Grid Region
Mountain West
Market
—
Developer
—
Utility
NV Energy
Entity
NVE
Service Type
—
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project NVE-Company 258