NVE-Company HN
45 MW generation in Washoe, NV · In queue since August 2017 · Proposed COD January 2026
45 MW
Capacity
1
Components
Geothermal
8y 9m
In Queue
IA Executed
IA Status
COD target: 2026
Total Duration
8y 5m
Schedule
3 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–36 months
Proposed COD: 2026-01-31
The NVE-Company HN development project is a proposed 45 MW geothermal generation facility located in Washoe County, Nevada. The project is listed in the NV Energy interconnection queue with a queue entry date of August 15, 2017, and a proposed commercial operation date of January 31, 2026. The project's interconnection agreement has been executed.
The project is being developed by NVE and consists of 45 MW of geothermal capacity. It is currently listed as an active project in the interconnection queue.
Generated from interconnection queue and public data sources
State
NV
County
Washoe
Grid Region
Mountain West
Market
—
Developer
—
Utility
NV Energy
Entity
NVE
Service Type
—
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project NVE-Company HN