NVE-Company HP
79 MW generation in Lander, NV · In queue since September 2017 · Proposed COD October 2027
79 MW
Capacity
1
Components
Solar
8y 8m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
10y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-10-15
The proposed NVE-Company HP project is a 79 MW solar generation project located in Lander County, Nevada. The developer is NV Energy (NVE). It is an active project in the NV Energy interconnection queue, with a queue entry date of September 27, 2017, and a proposed commercial operation date of October 15, 2027. The project's interconnection agreement has been executed.
Generated from interconnection queue and public data sources
State
NV
County
Lander
Grid Region
Mountain West
Market
—
Developer
—
Utility
NV Energy
Entity
NVE
Service Type
—
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project NVE-Company HP