NVE-Company HQ
240 MW hybrid in Pershing, NV · In queue since September 2017 · Proposed COD August 2024
240 MW
Capacity
1
Components
Solar
8y 8m
In Queue
Suspended
IA Status
COD target: 2024
Total Duration
6y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-08-01
The NVE-Company HQ development project is a proposed 240 MW hybrid solar and battery energy storage project located in Pershing County, Nevada. The project consists of 240 MW of solar photovoltaic generation. It is listed in the NV Energy interconnection queue as of September 27, 2017, with a proposed commercial operation date of August 1, 2024. The interconnection agreement (IA) status is currently suspended.
The project, sponsored by NVE, is currently listed as suspended in the interconnection queue.
Generated from interconnection queue and public data sources
State
NV
County
Pershing
Grid Region
Mountain West
Market
—
Developer
—
Utility
NV Energy
Entity
NVE
Service Type
—
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project NVE-Company HQ