NVE-Company IF
350 MW generation in Humboldt, NV · In queue since March 2018 · Proposed COD February 2026
350 MW
Capacity
1
Components
Solar
8y 2m
In Queue
IA Executed
IA Status
COD target: 2026
Total Duration
7y 11m
Schedule
3 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-02-01
The NVE-Company IF development project is a proposed 350 MW solar generation facility located in Humboldt County, Nevada. The project is sponsored by NV Energy and is currently active in the NV Energy interconnection queue, with an entry date of March 19, 2018. The project has an executed Interconnection Agreement (IA) and a proposed commercial operation date of February 1, 2026.
The project consists of 350 MW of solar photovoltaic generation capacity. The project has appeared in recent news coverage regarding NV Energy's renewable energy development plans.
Generated from interconnection queue and public data sources
State
NV
County
Humboldt
Grid Region
Mountain West
Market
—
Developer
—
Utility
NV Energy
Entity
NVE
Service Type
—
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project NVE-Company IF