NVE-Company IG
150 MW generation in Humboldt, NV · In queue since March 2018 · Proposed COD September 2023
150 MW
Capacity
1
Components
Solar
8y 2m
In Queue
IA Executed
IA Status
COD target: 2023
Total Duration
5y 6m
Schedule
33 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2023-09-01
The proposed NVE-Company IG project is a 150 MW solar generation facility located in Humboldt County, Nevada. The project is being developed by NVE and is interconnected with NV Energy. It consists of 150 MW of solar photovoltaic generation capacity.
The project is listed in the NV Energy interconnection queue as of March 19, 2018, with a proposed commercial operation date of September 1, 2023. The interconnection agreement for the project has been executed.
Generated from interconnection queue and public data sources
State
NV
County
Humboldt
Grid Region
Mountain West
Market
—
Developer
—
Utility
NV Energy
Entity
NVE
Service Type
—
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project NVE-Company IG