NVE-Company IL
200 MW hybrid in Washoe, NV · In queue since March 2018 · Proposed COD February 2027
200 MW
Capacity
1
Components
Solar
8y 2m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
8y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2027-02-01
The NVE-Company IL project is a proposed 200 MW solar and battery hybrid development in Washoe County, Nevada. The project consists of 200 MW of solar generation capacity. It is located in the West region and is being proposed by NV Energy (NVE).
The project is currently active in the NV Energy interconnection queue, with an initial queue entry date of March 29, 2018. The proposed commercial operation date is February 1, 2027, and the interconnection agreement has been executed.
Generated from interconnection queue and public data sources
State
NV
County
Washoe
Grid Region
Mountain West
Market
—
Developer
—
Utility
NV Energy
Entity
NVE
Service Type
—
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.