125 MW hybrid in Churchill, NV · In queue since September 2018 · Proposed COD December 2027
125 MW
Capacity
1
Components
Solar
7y 8m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
9y 3m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2027-12-01
The NVE-Company JE development project is a proposed 125 MW solar and battery hybrid project located in Churchill County, Nevada. The project consists of 125 MW of solar generation capacity.
The project is interconnected to the NV Energy system and is listed in the utility's interconnection queue as of September 26, 2018. The proposed commercial operation date is December 1, 2027, and the Interconnection Agreement (IA) has been executed.
Generated from interconnection queue and public data sources
State
NV
County
Churchill
Grid Region
Mountain West
Market
—
Developer
—
Utility
NV Energy
Entity
NVE
Service Type
—
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.