NVE-Company JW
100 MW storage in Washoe, NV · In queue since September 2019 · Proposed COD March 2027
100 MW
Capacity
1
Components
Battery
6y 8m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
7y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2027-03-30
NVE-Company JW is a proposed 100 MW battery storage project located in Washoe County, Nevada. The project is being developed within the NV Energy (NVE) service area. It entered the NV Energy interconnection queue on September 23, 2019, and has a proposed commercial operation date of March 30, 2027.
The project's interconnection agreement (IA) has been executed. Recent news coverage has discussed the project's potential impact on grid reliability in the West region.
Generated from interconnection queue and public data sources
State
NV
County
Washoe
Grid Region
Mountain West
Market
—
Developer
—
Utility
NV Energy
Entity
NVE
Service Type
—
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project NVE-Company JW