NVE-Company KD
750 MW hybrid in White Pine, NV · In queue since September 2019 · Proposed COD October 2026
750 MW
Capacity
1
Components
Hydro
6y 8m
In Queue
Suspended
IA Status
COD target: 2026
Total Duration
7y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-10-31
NVE-Company KD is a proposed 750 MW hybrid development project in White Pine County, Nevada. The project, located in the western region and interconnected with NV Energy (NVE), consists of a 750 MW hydro component and a battery component. It entered the NV Energy interconnection queue on September 30, 2019, with a proposed commercial operation date of October 31, 2026. The project's interconnection agreement status is currently suspended.
The project is listed as "suspended" in the interconnection queue. It has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
NV
County
White Pine
Grid Region
Mountain West
Market
—
Developer
—
Utility
NV Energy
Entity
NVE
Service Type
—
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project NVE-Company KD