38.5 MW generation in Esmeralda, NV · In queue since February 2020 · Proposed COD June 2022
38.5 MW
Capacity
1
Components
Geothermal
6y 3m
In Queue
IA Executed
IA Status
COD target: 2022
Total Duration
2y 4m
Schedule
48 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–36 months
Proposed COD: 2022-06-01
The NVE-Company KH development project is a proposed 38.5 MW geothermal generation facility located in Esmeralda County, Nevada. The project is listed in the NV Energy interconnection queue with a queue entry date of February 28, 2020, and a proposed commercial operation date of June 1, 2022. The project's interconnection agreement has been executed.
The project, sponsored by NVE, consists of 38.5 MW of geothermal capacity. The project is located in the Western region of the United States.
Generated from interconnection queue and public data sources
State
NV
County
Esmeralda
Grid Region
Mountain West
Market
—
Developer
—
Utility
NV Energy
Entity
NVE
Service Type
—
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project NVE-Company KH