NVE-Company KI
38.5 MW generation in Lyon, NV · In queue since February 2020 · Proposed COD May 2025
38.5 MW
Capacity
1
Components
Geothermal
6y 3m
In Queue
IA Executed
IA Status
COD target: 2025
Total Duration
5y 3m
Schedule
12 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–36 months
Proposed COD: 2025-05-01
The NVE-Company KI development project is a proposed 38.5 MW geothermal generation facility located in Lyon County, Nevada. The project is being developed by NVE and is interconnected with NV Energy. It entered the NV Energy interconnection queue on February 28, 2020, and has a proposed commercial operation date of May 1, 2025. The project's Interconnection Agreement (IA) has been executed.
The project consists of 38.5 MW of geothermal capacity. It is currently listed as active in the interconnection queue. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
NV
County
Lyon
Grid Region
Mountain West
Market
—
Developer
—
Utility
NV Energy
Entity
NVE
Service Type
—
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project NVE-Company KI