Project NVE-Company KW — Project Summary

Queue ID
NVE-Company KW
Capacity
250 MW
Technology
Battery
Status
suspended
Location
White Pine, NV
Region
West
Developer
IA Status
Suspended

NVE-Company KW

NVE-Company KWBetaSuspendedHydroBatteryNVELBNL

250 MW hybrid in White Pine, NV · In queue since September 2020 · Proposed COD December 2026

250 MW

Capacity

1

Components

Hydro

5y 8m

In Queue

Suspended

IA Status

COD target: 2026

Interconnection

Total Duration

6y 3m

Suspended38%
Queue EntrySep 23, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-31

About

The NVE-Company KW development project is a proposed 250 MW hybrid facility located in White Pine County, Nevada. The project, developed by NVE, combines hydro and battery technologies, with 250 MW attributed to hydro.

The project is in the NV Energy interconnection queue, having entered on September 23, 2020. The proposed commercial operation date is December 31, 2026. The interconnection agreement status is currently suspended.

Generated from interconnection queue and public data sources

Project Details

State

NV

County

White Pine

Grid Region

Mountain West

Market

Developer

Utility

NV Energy

Entity

NVE

Service Type

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
PALOVERDE
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project NVE-Company KW