NVE-Company LD
200 MW hybrid in Lander, NV · In queue since March 2021 · Proposed COD December 2029
200 MW
Capacity
1
Components
Solar
5y 2m
In Queue
Suspended
IA Status
COD target: 2029
Total Duration
8y 9m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-31
The NVE-Company LD project is a proposed 200 MW hybrid solar and battery energy storage project located in Lander County, Nevada. The developer is NVE, and the project is interconnected with NV Energy. It consists of 200 MW of solar generation capacity.
The project is listed in the NV Energy interconnection queue as of March 29, 2021, with a proposed commercial operation date of December 31, 2029. Its interconnection agreement status is currently suspended. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
NV
County
Lander
Grid Region
Mountain West
Market
—
Developer
—
Utility
NV Energy
Entity
NVE
Service Type
—
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.