NVE-Company LK
200 MW hybrid in Lyon, NV · In queue since March 2021 · Proposed COD December 2029
200 MW
Capacity
1
Components
Solar
5y 2m
In Queue
IA Executed
IA Status
COD target: 2029
Total Duration
8y 9m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2029-12-31
The NVE-Company LK development project is a proposed 200 MW hybrid solar and battery energy storage project located in Lyon County, Nevada. The project is listed in the NV Energy interconnection queue with a queue entry date of March 31, 2021, and a proposed commercial operation date of December 31, 2029.
The project consists of 200 MW of solar photovoltaic generation co-located with battery energy storage. The interconnection agreement for the project has been executed. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
NV
County
Lyon
Grid Region
Mountain West
Market
—
Developer
—
Utility
NV Energy
Entity
NVE
Service Type
—
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project NVE-Company LK