NVE-Company LM
230 MW generation in Lyon, NV · In queue since March 2021 · Proposed COD December 2029
230 MW
Capacity
1
Components
Geothermal
5y 2m
In Queue
Suspended
IA Status
COD target: 2029
Total Duration
8y 9m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-31
The NVE-Company LM development project is a proposed 230 MW geothermal generation facility located in Lyon County, Nevada. The project, sponsored by NV Energy (NVE), entered the NV Energy interconnection queue on March 31, 2021. Its proposed commercial operation date is December 31, 2029.
The project's interconnection status is currently listed as "suspended," and its Interconnection Agreement (IA) status is also "Suspended." The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
NV
County
Lyon
Grid Region
Mountain West
Market
—
Developer
—
Utility
NV Energy
Entity
NVE
Service Type
—
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project NVE-Company LM