NVE-Company LS
180 MW generation in Lyon, NV · In queue since September 2021 · Proposed COD September 2024
180 MW
Capacity
1
Components
Wind
4y 8m
In Queue
Suspended
IA Status
COD target: 2024
Total Duration
3 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-09-01
The NVE-Company LS project is a proposed 180 MW wind generation project located in Lyon County, Nevada. The project is being developed by NVE and is interconnected to the NV Energy system.
The project entered the NV Energy interconnection queue on September 28, 2021, with a proposed commercial operation date of September 1, 2024. Its interconnection agreement status is currently listed as suspended.
Generated from interconnection queue and public data sources
State
NV
County
Lyon
Grid Region
Mountain West
Market
—
Developer
—
Utility
NV Energy
Entity
NVE
Service Type
—
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project NVE-Company LS