NVE-Company LU
700 MW hybrid in Mineral, NV · In queue since September 2021 · Proposed COD December 2029
700 MW
Capacity
1
Components
Solar
4y 8m
In Queue
IA Executed
IA Status
COD target: 2029
Total Duration
8y 3m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2029-12-31
The proposed NVE-Company LU project is a 700 MW hybrid solar and battery energy storage development in Mineral County, Nevada. The project consists of 700 MW of solar photovoltaic generation.
The project is in the NV Energy interconnection queue, with an entry date of September 28, 2021. Its proposed commercial operation date is December 31, 2029, and the interconnection agreement has been executed. The developer is NVE.
Generated from interconnection queue and public data sources
State
NV
County
Mineral
Grid Region
Mountain West
Market
—
Developer
—
Utility
NV Energy
Entity
NVE
Service Type
—
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.