NVE-Company LW
550 MW hybrid in Mineral, NV · In queue since September 2021 · Proposed COD December 2029
550 MW
Capacity
1
Components
Solar
4y 8m
In Queue
Suspended
IA Status
COD target: 2029
Total Duration
8y 3m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-31
The NVE-Company LW project is a proposed 550 MW hybrid solar and battery energy storage development in Mineral County, Nevada. The project, located in the western United States, consists of 550 MW of solar generation capacity. It is listed in the NV Energy interconnection queue as of September 29, 2021, with a proposed commercial operation date of December 31, 2029.
The interconnection agreement (IA) for the project is currently listed as suspended, and the overall project status is also suspended.
Generated from interconnection queue and public data sources
State
NV
County
Mineral
Grid Region
Mountain West
Market
—
Developer
—
Utility
NV Energy
Entity
NVE
Service Type
—
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.