NVE-Company MB
300 MW hybrid in White Pine, NV · In queue since September 2021 · Proposed COD December 2028
300 MW
Capacity
1
Components
Solar
4y 8m
In Queue
IA Executed
IA Status
COD target: 2028
Total Duration
7y 3m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2028-12-31
The NVE-Company MB project is a proposed 300 MW solar and battery hybrid development in White Pine County, Nevada. The project consists of 300 MW of solar generation, paired with battery storage. It is located in the West region and is being developed by NVE.
The project is currently active in the NV Energy interconnection queue, with an interconnection queue entry date of September 29, 2021. The proposed commercial operation date is December 31, 2028, and the Interconnection Agreement has been executed.
Generated from interconnection queue and public data sources
State
NV
County
White Pine
Grid Region
Mountain West
Market
—
Developer
—
Utility
NV Energy
Entity
NVE
Service Type
—
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project NVE-Company MB