NVE-Company MI
700 MW hybrid in Churchill, NV · In queue since September 2021 · Proposed COD September 2024
700 MW
Capacity
1
Components
Solar
4y 8m
In Queue
IA Executed
IA Status
COD target: 2024
Total Duration
3 years
Schedule
20 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2024-09-01
NVE-Company MI is a proposed 700 MW hybrid solar and battery project located in Churchill County, Nevada. The development project consists of 700 MW of solar capacity. It is being proposed by NVE and is in the NV Energy interconnection queue, with an entry date of September 30, 2021. The project's proposed commercial operation date is September 1, 2024, and the interconnection agreement has been executed.
The project is listed as active in the interconnection queue. Recent news coverage has discussed the project's progress and potential impact on the region's energy landscape.
Generated from interconnection queue and public data sources
State
NV
County
Churchill
Grid Region
Mountain West
Market
—
Developer
—
Utility
NV Energy
Entity
NVE
Service Type
—
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.