NVE-Company MN
1.3 MW hybrid in Lyon, NV · In queue since December 2021 · Proposed COD June 2022
1.3 MW
Capacity
1
Components
Solar
4y 5m
In Queue
IA Executed
IA Status
COD target: 2022
Total Duration
6 months
Schedule
48 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2022-06-01
The NVE-Company MN development project is a proposed hybrid solar and geothermal project with a total capacity of 1.3 MW, located in Lyon County, Nevada. The project consists of 1.3 MW of solar generation. It is listed in the NV Energy interconnection queue with a queue entry date of December 21, 2021, and a proposed commercial operation date of June 1, 2022. The project's interconnection agreement has been executed.
The project is being developed by NVE. It is currently listed as active in the interconnection queue. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
NV
County
Lyon
Grid Region
Mountain West
Market
—
Developer
—
Utility
NV Energy
Entity
NVE
Service Type
—
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project NVE-Company MN