NVE-Company NH
100 MW storage in Washoe, NV · In queue since March 2022 · Proposed COD April 2024
100 MW
Capacity
1
Components
Battery
4y 2m
In Queue
Suspended
IA Status
COD target: 2024
Total Duration
2y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-04-01
The NVE-Company NH development project is a proposed 100 MW battery storage facility located in Washoe County, Nevada. The project is being developed by NVE and is interconnected with NV Energy. It entered the NV Energy interconnection queue on March 29, 2022, with a proposed commercial operation date of April 1, 2024.
Currently, the project's interconnection agreement status is listed as suspended. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
NV
County
Washoe
Grid Region
Mountain West
Market
—
Developer
—
Utility
NV Energy
Entity
NVE
Service Type
—
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project NVE-Company NH