NVE-Company NS
300 MW hybrid in Eureka, NV · In queue since September 2022 · Proposed COD November 2029
300 MW
Capacity
1
Components
Solar
3y 8m
In Queue
Suspended
IA Status
COD target: 2029
Total Duration
7y 2m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-11-15
NVE-Company NS is a proposed 300 MW hybrid solar and battery project located in Eureka County, Nevada. The development project, under the utility NV Energy and developer NVE, consists of 300 MW of solar capacity. It is currently listed as "suspended" in the NV Energy interconnection queue, with an entry date of September 22, 2022, and a proposed commercial operation date of November 15, 2029. The interconnection agreement (IA) status is also listed as "suspended".
The project is located in the western region of the United States. It is a hybrid project, combining solar and battery technologies. The project has appeared in recent news coverage regarding renewable energy development in Nevada.
Generated from interconnection queue and public data sources
State
NV
County
Eureka
Grid Region
Mountain West
Market
—
Developer
—
Utility
NV Energy
Entity
NVE
Service Type
—
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.