NVE-Company NU
600 MW hybrid in White Pine, NV · In queue since September 2022 · Proposed COD November 2029
600 MW
Capacity
1
Components
Solar
3y 8m
In Queue
Suspended
IA Status
COD target: 2029
Total Duration
7y 2m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-11-15
The NVE-Company NU development project is a proposed 600 MW solar and battery hybrid project located in White Pine County, Nevada. The project consists of 600 MW of solar capacity. It is in the NV Energy interconnection queue, with an entry date of September 22, 2022, and a proposed commercial operation date of November 15, 2029. The project's interconnection agreement status is currently suspended.
The project, located in the western region of the United States, is listed in the interconnection queue under the entity NVE. The project's overall status is also listed as suspended.
Generated from interconnection queue and public data sources
State
NV
County
White Pine
Grid Region
Mountain West
Market
—
Developer
—
Utility
NV Energy
Entity
NVE
Service Type
—
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.